收藏本站
设为首页收藏本站

【天端--工程在线】

 找回密码
 注册

QQ登录

只需一步,快速开始

查看: 3910|回复: 3
打印 上一主题 下一主题

某英联邦国家国家道路工程施工规范(英文版)副主要注释

[复制链接]
跳转到指定楼层
1
发表于 2006-8-13 21:37:00 | 只看该作者 回帖奖励 |倒序浏览 |阅读模式
TECHNICAL SPECIFICATIONS

Series 1000:        GENERAL

1100   Definitions and Terms

1200   General Requirement and Provisions

1300   Contractors Establishment
1301   SCOPE
1302   GENERAL REQUIREMENTS
1303   PAYMENT

1400   Accommodation, Services and Attendance for the Engineer’s staff
1401   SCOPE
1402   OFFICE AND LABORATORY ACCOMMODATION
1403   ENGINEER'S OFFICE
1404   LABORATORY
1405   SERVICES
1406   TIME FOR PROVISION OF ENGINEER'S OFFICE, LABORATORY AND EQUIPMENT
1407   VEHICLES
1408   ATTENDANCE
1409   MEASUREMENT AND PAYMENT

1500   Environmental Protection
1501   GENERAL
1502   LAND ACQUISITION
1503   CONTRACTOR’S ACTIVITIES IN RESPECT OF PROPERTY OUTSIDE THE SITE BOUNDARY  AND SERVICES MOVED, ALTERED OR DAMAGED
1504   ENTRY UPON LAND WITHIN THE SITE BOUNDARY
1505   PAYMENT OF ROYALTY FOR CONSTRUCTION MATERIALS
1506   CONSTRUCTION CAMPS
1507   RESTORATION OF CONSTRUCTION CAMP SITES
1508   (a)        EROSION CONTROL
           (b)        ESTABLISHMENT OF VEGETATION
           (c)        TRAPS, BENCH, TOE AND ROADSIDE DRAINS
           (d)        SILT FENCES
1509   CLEARING
1510   DISPOSAL OF UNSUITABLE OR EXCESS MATERIALS
1511   EXTRACTION OF RIVER GRAVELS
1511   (a)        RIVER GRAVEL EXTRACTION MANAGEMENT PLAN
           (b)        VEGETATION PROTECTION
           (c)        CONDITION OF PLANT AND MACHINERY
           (d)        FUEL STORAGE AND REFUELLING
           (e)        SITE RESTORATION
1512   QUARRYING AND BLASTING
1512.1   QUARRY MANAGEMENT PLAN
1512.2   VISUAL IMPACT QUARRIES
1512.3   SAFETY PROVISIONS AT QUARRY
1512.4   FIRST AID
1512.5   QUARRY MANAGER
1512.6   VEGETATION
1512.7   OVERBURDEN STRIPPING
1512.8   BLASTING
1512.9   DUST SUPPRESSION
1513   MEASUREMENT AND PAYMENT

1600  Overhaul

1700  Clearing and Grubbing
1701  SCOPE
1702   DESCRIPTION OF WORK
1703   EXECUTION OF WORK
1704   MEASUREMENT AND PAYMENT

1800   Accommodation of traffic
1801   SCOPE
1802   GENERAL REQUIREMENTS
1803   BARRICADES AND TRAFFIC SIGNS
1804   WIDTH OF BYPASSES
1805   TEMPORARY DRAINAGE WORKS
1806   CONSTRUCTION OF BYPASSES
1807   MAINTENANCE OF EXISTING ROAD AND GRAVEL BYPASSES
1808   ACCOMMODATION OF TRAFFIC WHERE THE ROAD IS CONSTRUCTED IN HALF WIDTHS
1809   THE CONTRACTOR'S USE OF BYPASSES
1810   REMOVAL OF BYPASSES       
1811   TREATMENT OF SECTIONS OF EXISTING ROAD NO LONGER REQUIRED
1812   MEASUREMENT AND PAYMENT

Series 2000:        SURFACE WATER DRAINAGE

2100   Drains
2101   SCOPE
2102   OPEN DRAINS
2103   BANKS AND DYKES
2104   SUB-SURFACE DRAINS
2105   CLASSIFICATION OF EXCAVATION
2106   MEASUREMENT AND PAYMENT

2200   Prefabricated Culverts and Stormwater Sewers
2201   SCOPE
2202   TYPES OF CULVERTS
2203   MATERIALS
2204   CONSTRUCTION METHODS
2205   DEPTH OF EXCAVATION
2206   WIDTH OF EXCAVATION
2207   UNSUITABLE FOUNDING CONDITIONS
2208   EXCAVATION FOR EMBANKMENT CONDITIONS
2209   CLASSIFICATION OF EXCAVATION
2210   DISPOSAL OF EXCAVATION
2211   BEDDING AND LAYING OF PREFABRICATED CULVERTS AND         STORMWATER SEWERS
2212   BACKFILLING OF PREFABRICATED CULVERTS AND STORMWATER SEWERS
2213   INLET AND OUTLET STRUCTURES, CATCHPITS AND MANHOLES
2214   REMOVAL OF EXISTING WORK
2215   CONCRETE INVERT IN CORRUGATED STEEL CULVERTS
2216   SERVICE DUCTS
2217   (NOT UTILISED)
2218   MEASUREMENT AND PAYMENT

2300   Concrete Kerbing, Channelling, Open concrete chutes and concrete lining of open drains
2301   SCOPE
2302   MATERIALS
2303   TYPES OF STRUCTURES
2304   CONSTRUCTION
2305   INLET AND OUTLET STRUCTURES AND TRANSITION SECTIONS
2306   CONSTRUCTION TOLERANCES AND SURFACE FINISH
2307   MEASUREMENT AND PAYMENT

2400   Pitching, Stonework and erosion protection
2401   SCOPE
2402   MATERIALS
2403   STONE PITCHING
2404   RIPRAP
2405   STONE MASONRY WALLS
2406   CONCRETE BLOCK PITCHING
2407   CAST IN SITU CONCRETE PITCHING
2408   MEASUREMENT AND PAYMENT

Series 3000:        EARTHWORKS, SUB-BASE AND BASECOURSE

3100   Earthworks General
3200   Excavation
3300   Construction of Embankments
3400   Gravel Wearing Course
3500   Sub-base
3600   Basecourse
3700   Stabilisation

Series 4000:        SEALING

4100   Prime Coat
4200   Double seal surface treatment
         
Series 5000:        ANCILLARY WORKS

5100   Gabions
5200   Guide Posts, Market Posts and Kilometre posts
5300   Guardrails
5400   Road Signs and Bus Shelters               
5500   Road Traffic Markings and Roadstuds
5600   Topsoiling and Landscaping
5700   Finishing of Road, Road reserve and other areas within the site
         
Series 6000:        STRUCTURES

6100   Foundations for Structures
6200   Falsework, Formwork and Concrete Finish
6300   Steel Reinforcement for Structures
6400   Concrete for Structures
6500   Prestressing
6600   No Fines Concrete
6700   Joints in Structures
6800   Bearings for Structures
6900   Bridge parapets, Railings and Sitewalks

Series 7000:        STRUCTURES

7100   Not used
7200   Bridge drainage and surface ducts
7300   Construction Tolerances for Structures
7400   Demolition of existing structures

Series 8000:        NOT USED

Series 9000:        MATERIALS AND TESTING

9100   Materials
9200   Testing
分享到:  QQ好友和群QQ好友和群 QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
收藏收藏 分享分享 支持支持 反对反对
2
 楼主| 发表于 2006-8-13 21:38:39 | 只看该作者
这个是我在国外工作时的项目所采用的施工规范,我将逐步逐步的发上来,跟大家一起讨论,研习!欢迎大家就本贴提出意见!
回复 支持 反对

使用道具 举报

3
 楼主| 发表于 2006-8-21 17:24:43 | 只看该作者
SERIES 1000: GENERAL


1100        DEFINITIONS AND TERMS

1200        GENERAL REQUIREMENT AND PROVISIONS

1300        CONTRACTORS ESTABLISHMENT

1400        ACCOMMODATION, SERVICES AND ATTENDANCES FOR THE ENGINEER'S STAFF

1500        ENVIRONMENTAL PROTECTION

1600        OVERHAUL

1700        CLEARING AND GRUBBING

1800        ACCOMMODATION OF TRAFFIC


SECTION 1100:   DEFINITIONS AND TERMS

        CONTENTS

1101        ASPHALT                               

1102        ASPHALT SURFACING               

1103        BASE                                       

1104        BORROW MATERIAL                       

1105        BORROW AREA                       

1106        BRIDGE                               

1107        CARRIAGEWAY                       

1108        CATCHWATER DRAIN OR BANK       

1109        CULVERT                               

1110        CUT AND BORROW                       

1111        EXCESS OVERBURDEN               

1112        FILL                                       

1113        GRADE LINE                               

1114        GRADING MODULUS (GM)               

1115        INLET AND OUTLET DRAIN               

1116        LOT                                       

1117        MEDIAN                               

1118        MEDIAN DRAIN                               

1119        MITRE DRAIN AND BANK               

1120        PAVEMENT LAYER                       

1121        PIONEER LAYER                       

1122        ROAD BED

1123        ROAD PRISM

1124        SELECTED SUBGRADE MATERIAL

1125        SIDE FILL

1126        SIDE DRAIN

1127        SHOULDER

1128        SHOULDER BREAKPOINT

1129        STABILISATION

1130        SLOPE

1131        SPOIL (MATERIAL)

1132        SUBBASE

1133        SUBGRADE

1134        SUBSURFACE DRAIN

1135        SURFACE TREATMENT

1136        TRAVELLED WAY

1137        EARTHWORKS

1138        QUARRY SITE

1139        PRIME COAT

1140        SEAL COAT

1141        SITE                       


In these Specifications the following terms, words or expressions shall have the meanings hereby assigned to them except where the context otherwise requires.


1101        ASPHALT
A mixture to predetermined proportions of aggregate, filler and bituminous binder material prepared off the road and usually placed by means of a paving machine.

1102        ASPHALT SURFACING
The  layer  or  layers  of  asphalt  constructed  on top  of the  base, and, in  some cases,   the         shoulders.

1103        BASE
A layer of material of defined thickness and width constructed on top of the subbase, or in the absence thereof, the sub-grade. A base may extend to outside the travelled way.

1104        BORROW MATERIAL
Any gravel, sand, soil, rock or ash obtained from borrow areas, dumps or sources other than cut within the road prism and which is used in the construction of the Works.It shall not include crushed stone or sand obtained from commercial sources.

1105        BORROW AREA
An area within designated boundaries, approved for the purpose of obtaining borrow material.  A borrow pit is the excavated pit in a borrow area.

1106        BRIDGE
A structure erected over a depression, river, watercourse, railway line, road or other obstacle for carrying motor, railway, pedestrian or other traffic or services and having a length, measured between abutment faces along centre line at girder bed level, of 6 m or more.

1107        CARRIAGEWAY
The area normally travelled by vehicles and consisting of one or a number of contiguous traffic lanes, including auxiliary lanes and shoulders.

1108        CATCHWATER DRAIN OR BANK
A longitudinal drain or bank outside the road prism for diverting water that would otherwise flow onto the road prism.

1109        CULVERT
A structure, other than a bridge, which provides an opening under the carriageway or median for drainage or other purposes.

1110        CUT AND BORROW
Cut shall mean all excavations from the road prism including side drains, excavations for intersecting roads including interchanges and, where classified as cut, excavations for open drains.The term borrow shall apply to all borrow materials.

1111        EXCESS OVERBURDEN
Overburden within a borrow area which is not required or is unsuitable for use in construction.

1112        FILL
That portion of the earthworks composed of approved imported material which lies above the road bed and is bounded by the side slopes, shown on the typical cross sections on the Drawings, running downwards and outwards from the outer shoulder breakpoints and on which the subbase, base, shoulders and, in the case of dual carriageways, the median are to be constructed.  Material which is imported to replace unsuitable material excavated from the road bed shall also be classified as fill.

1113        GRADE LINE
The grade line is a reference line on the Drawings of the longitudinal sections of the road indicating at regular intervals the elevations according to which the road is to be constructed.  The grade line refers to the surface level of the completed basecourse.

1114        GRADING MODULUS (GM)
The cumulative percentages by mass of material in a representative sample of aggregate, gravel or soil retained on the 2.00 mm; 0.425 mm and 0.075 mm sieves, divided by 100.

1115        INLET AND OUTLET DRAIN
Channels leading into or discharging from culverts, stormwater conduits and minor bridges.

1116        LOT
A sizeable portion of work or quantity of material which is assessed  by the Engineer as a unit for the purpose of quality control and selected to represent material or work produced by essentially the same process and materials.

1117        MEDIAN
The area between the two travelled ways of a dual carriageway road.  It includes the inside shoulders.

1118        MEDIAN DRAIN
Longitudinal drain situated between the inside shoulders of a dual carriageway road.

1119        MITRE DRAIN AND BANK
Drain constructed at an angle to the centre line of the road to divert water from the side drains.  Mitre drains will include mitre banks placed across side drains.

1120        PAVEMENT LAYER
The upper layers of the road comprising the subbase, base, shoulders and surfacing.

1121        PIONEER LAYER
An initial layer constructed over a weak road bed using selected material to provide a stable surface for the construction of subsequent layers.

1122        ROAD BED
The natural in situ material on which the fill, or in the absence of fill, any pavement layers, are to be constructed.

123        ROAD PRISM
That portion of the road construction included between the original ground level and the outer lines of the slopes of cuttings, fills, side fills and side drains.  It shall not include subbase, base, surfacing, shoulders or road bed.

1124        SELECTED SUBGRADE MATERIAL
Material used in the  upper layer or layers of the subgrade (when provision is made for such a classification in the Drawings and Bill of Quantities) which is controlled both in quality and density by requirements more stringent than those for common fill.  It may include suitable road bed material compacted in situ but does not include material that has been stabilised..

1125        SIDE FILL
That portion of the imported material within the road prism which lies outside the fills, shoulders, base and subbase and is contained within such surface slopes as shown on the Drawings or as directed by the Engineer.  

1126        SIDE DRAIN
Open longitudinal drain situated adjacent to and at the bottom of cut or fill slopes.

1127        SHOULDER
(a)        When referring to this as a surface:  the area between the outside edge of the travelled way and the shoulder breakpoint.
(b)         When referring to this as a pavement layer:  the layer on top of the subbase or, in the absence of a subbase, on top of the sub-grade and lying between the outside edge of the base and the shoulder breakpoint.

1128        SHOULDER BREAKPOINT
The line along which the extended flat planes of the surface of the shoulder and the outside slope of the fill and pavement intersect.  This edge is normally rounded to a predetermined radius.

1129        STABILISATION
The treatment of the materials used in the construction of the road bed fill or pavement layers by the addition of a cementitious binder such as lime or Portland Cement or the mechanical modification of the material through the addition of a soil binder.  Concrete and asphalt shall not be considered as materials that have been stabilised.

1130        SLOPE
Unless otherwise stated, is given in terms of the ratio of vertical difference in elevation between any two points and the horizontal distance between them.
This ratio may also be expressed as a percentage.

1131        SPOIL (MATERIAL)
Material originating from construction operations and which is not utilised for construction purposes.

1132        SUBBASE
The layer of material of specified dimensions on top of the sub-grade and below base and shoulders.

1133        SUBGRADE
That portion of the earthworks either remaining in cut or constructed in fill or in cut which is situated in the zone 500mm immediately below the underside of subbase or in the absence of the subbase, the base layer

1134        SUBSURFACE DRAIN
Covered drain constructed to intercept and remove subsoil water, including any pipes and permeable material in the drains.

1135        SURFACE TREATMENT
The sealing or resealing of the carriageway or shoulders by means of one or more successive applications of bituminous binder and crushed stone aggregate.

1136        TRAVELLED WAY
That portion of the carriageway including the various traffic lanes and auxiliary lanes but excluding shoulders.

1137        EARTHWORKS
That portion of the road construction that encompasses the fill (including the subgrade) and excavation in cut and borrow including open drains as defined in Clause
2102 (b).

1138        QUARRY SITE
A borrow area within designated boundaries, approved for the purpose of obtaining crushed stone and aggregate or other materials  for use in the Works.

1139        PRIME COAT
That coat which is applied to a new base prior to any other coat.

1140        SEAL COAT
That coat, in the case of new work, that is applied to the prime coat.

1141        SITE
The area shown on the drawings as being occupied by the Permanent Works plus an addition width of 3 metres each side measured at right angles to the centreline beyond the point at which the fill profile or cut profile shown on drawings intersects the existing ground, or 3 metres beyond any side drain or toe drain forming part of the Permanent Works.
The Site shall also include any area outside the limits as described upon which permanent works are to be executed under the instructions of the Engineer, e.g. inlet and outlet channels to drainage structures, permanent property access etc.  
For the purpose of the Contractors obligations with regard to maintenance of the existing road, demolition of existing bridges and restoration of existing road, the Site shall be taken to include all that area occupied by the existing road whether it lies within the site boundary as defined above or not.

[ 本帖最后由 laffee 于 2006-8-21 17:31 编辑 ]
回复 支持 反对

使用道具 举报

4
 楼主| 发表于 2006-8-21 17:35:17 | 只看该作者
SECTION 1200:   GENERAL REQUIREMENTS AND PROVISIONS

        CONTENTS

1201        SCOPE

1202        SERVICES

1203        ROAD INTERSECTIONS AND JUNCTIONS

1204        PROGRAMME OF WORK

1205        WORKMANSHIP AND QUALITY CONTROL

1206        SETTING OUT OF WORK AND PROTECTION OF BEACONS

1207        NOTICES, SIGNS AND ADVERTISEMENTS

1208        MEASUREMENT

1209        PAYMENT

1210        SUBSTANTIAL COMPLETION OF THE WORKS

1211        HAUL OVER COMPLETED ROAD

1212        NOT USED

1213        NOT USED

1214        EXTENSION OF TIME ARISING FROM ABNORMAL RAINFALL

1215        NOT USED

1216        INFORMATION FURNISHED BY THE EMPLOYER

1217        NOT USED

1218        PROTECTION OF THE WORKS AND REQUIREMENTS TO BE MET BEFORE CONSTRUCTION OF NEW WORK ON TOP OF COMPLETED WORK IS COMMENCED

1219        REMEDIAL WORK

1220        WATER

1221        ELECTRICITY SUPPLY

1222        PAYMENTS AND TOLERANCES
       
1223        DRAWINGS

1224        NOT USED

1225        PHOTOGRAPHIC RECORDS

1226        (NOT USED)

1227        ACCESS TO SITE

1228        CO-OPERATION AT SITE

1229        ROADS AND SITE TO BE KEPT CLEAN

1230        SECURITY OF THE WORKS

1231        SUPPRESSION OF NOISE

1232        SAFETY

1233        METHOD OF WORKING

1234        TEMPORARY WORKS





SECTION 1200:   GENERAL REQUIREMENTS AND PROVISIONS

1201        SCOPE

        This section covers matters which relate to the construction work as a whole.  Definitions, phrases or wording which would otherwise require repetition in other sections of the Specifications are also covered by clauses in this section.  Matters covered by the General Conditions of Contract are not repeated in this section, except where necessary in order to provide more detailed information.

1202        SERVICES

        This Contract may include certain work involved in moving and reinstating existing services that may be affected by the construction of the Works.

        The Employer will provide in the Contract Documents information regarding the location of existing utility services, but the Employer does not accept responsibility for the accuracy of this information.

        Where the position of a known service cannot be determined with sufficient accuracy by visual inspection, the Contractor shall open up and make further investigations before commencing construction, so that the position of such services can be determined with sufficient accuracy to avoid damage during construction.  Where so instructed, the Contractor shall also open up and search for any services not shown on the plans but which he or the Engineer may believe to exist.  Thereafter the Contractor shall assume responsibility for all known services whether shown on the Drawings or not.

        The Contractor shall take all reasonable precautions to protect existing services during construction and during relocation of such services.  Any pipe, cable, conduit or other known service of any nature whatsoever damaged as a result of the Contractor's operations, shall be repaired and reinstated forthwith by the Contractor or by the Authority concerned, all at the expense of the Contractor and to the satisfaction of the Engineer.

        It shall be clearly understood that in certain instances existing services can only be relocated after the Contractor had advanced sufficiently on, or completed, certain sections of earthworks or certain structures.

        Whenever services are encountered which interfere with the execution of the Works and which require to be moved and relocated, the Contractor shall advise the Engineer, who will determine the extent of the work, if any, to be undertaken by the Contractor in removing, relocating and reinstating or protecting such services.

        Any work required to be undertaken by the Contractor in protecting or moving and relocating services shall be valued in accordance with Clause 58 of the General Conditions of the Contract and a Provisional Sums are included for this purpose in the Bills of Quantity (Bill No 6, Ancillary Works).  Where the Contractor is required to make payment under the provisional sums to any statutory body (including Telecom Fiji, Fiji Electricity Authority and Public Works Department) for work done by them in relocating services, the Engineer shall certify only the actual amount paid for reimbursement to the Contractor.  Any administrative expense or cost of liaising with each authority shall be deemed to be included in item 13.01(b).

        The Contractor shall work in close co-operation with private owners or public authorities controlling services which have to be protected, removed or relocated.  Details regarding the state of negotiations concluded between the Employer and the owner at the time of tendering in respect of the time at which either the owner is prepared to start moving such services or at which the Contractor is required to or will be allowed to start moving services and the duration of such operations, will either be stated in the Tender Documents or be made available to Tenderers.

        When the Contractor details his programme of work he shall, in consultation with the Engineer, clearly indicate when he proposes to start and conclude the moving of each service or when he will require the owner to start and conclude the moving of each service.  Should it thereafter, through delays on the part of the Employer or the owner of the service  not be possible to carry out the relocation work within the planned time frame, such programme shall be suitably altered by the Contractor in consultation with the Engineer so as to limit, as far as possible, the extent of any damages or delays.  Should it not be possible to limit entirely the damages or delays resulting from the alterations necessary to the programme of work, the Contractor shall be reimbursed for any additional costs or damages incurred by him.

        The Contractor's attention is drawn to the need for Telecom Fiji  and the Fiji Electricity Authority to carry out extensive relocation works on both the Lodoni and Kings roads. The Contractor shall liaise with Telecom Fiji and the Fiji Electricity Authority to allow them or their agents or contractors reasonable access to any part of the site.  The position of the new lines will be adjacent to the contract road and work on the repositioning will be carried out during the contract period. In the case of Telecom lines, some sections may be placed in underground ducts.

1203        ROAD INTERSECTIONS AND JUNCTIONS

        Except where otherwise specified, no additional payment over and above payment for the various items or work included under this Contract will be made for the construction, in confined surroundings of curves, tapers, bell-mouths, traffic islands, farm accesses and other appurtenant works connected with the construction and maintenance of road intersections and junctions.

        The Contractor shall be required to provide for the safe and unrestricted flow of public traffic at all times during the construction and maintenance of such intersections and junctions.

1204        PROGRAMME OF WORK

        The programme of work required in terms of the General Conditions of Contract shall be submitted to the Engineer not later than 28 days after the Contractor has been issued with the order to commence.

        The Programme shall not be in the form of a bar chart only, but shall show clearly the anticipated quantities of work to be performed each month, the resources to be applied to each activity as well as the anticipated earnings for the various sections of work.


        The programme shall also show the order in which the Contractor plans to accept responsibility for maintenance of sections of existing road both on and off the site.
        If, during the progress of the work, the quantities of work performed per month fall below those shown in the programme, or if the sequence of operations is altered, or if the programme is deviated from in any other way, the Contractor shall, within one week after being notified by the Engineer, submit a revised programme.

       

        If the programme is to be revised by reason of the Contractor falling behind his programme, he shall produce a revised programme showing the modifications to the original programme necessary to ensure completion of the works or any part thereof within the time for completion as defined in Clause 43 of the Conditions of Contract or any extended time granted pursuant to Clause 44 of the Conditions of Contract.  Any proposal to increase the tempo of the work must be accompanied by positive steps to increase production by providing more labour and plant on Site, or by using the available labour and plant in a more efficient manner.

        Failure on the part of the Contractor to work according to the programme or revised programme, shall be sufficient reason for the Employer to take steps as provided for in the Conditions of Contract and shall be construed, as not executing the Works in accordance with the Contract.

        The approval by the Engineer of any programme shall have no contractual significance other than that the Engineer would be satisfied if the work is carried out according to such programme and that the Contractor undertakes to carry out the work in accordance with the programme, nor shall it limit the right of the Engineer to instruct the Contractor to vary the programme should circumstances make this necessary.  The above shall not be taken to limit the right of the Contractor to claim for damages or extension of time to which he may be fairly entitled to in terms of the General Conditions of Contract for delay or disruption of his activities.

        Should the Employer request and the Contractor undertake to finish the whole or part of the Works ahead of the time originally required by the Contract, payment for accelerating the work shall only be made if agreed to beforehand in writing and according to the terms of such agreement.

1205        WORKMANSHIP AND QUALITY CONTROL

        The onus is on the Contractor to produce work which conforms in quality and accuracy of detail to the requirements of the Specifications and Drawings, and the Contractor must, at his own expense, institute a quality control system and provide experienced engineers, foremen, surveyors, materials technicians, other technicians and other technical staff, together with all transport, instruments and equipment, to ensure adequate supervision and positive control of the Works at all times.

        The cost of all supervision and process control, including testing, so carried out by the Contractor, shall be deemed to be included in the rates tendered for the related items of work except that the cost of certain tests and the provision of certain items of testing and sampling equipment will be paid for separately as provided for in those sections of the Specifications where this applies.

        Unless otherwise instructed by the Engineer, the Contractor shall obtain approval for each layer of the works, in embankments, sub-grade, any stabilised layers, subbase, base and surfacing and shall not proceed with subsequent layers until each approval is granted.  The Contractor shall be required to give a minimum of 24 hours notice in writing to the Engineer to allow any inspection to be carried out.  If any test is required to verify compliance with these specifications, then the Contractor shall plan his Works so as to allow the Engineer sufficient time to carry out such tests.  Unless instructed otherwise, the Contractor may proceed with the Works even though the results of tests may not yet be available.  However, the Contractor shall be required to re-execute work if tests indicate non compliance with these Specifications.  Any approval given by the Engineer shall not relieve the Contractor of any of his obligations under the Contract.

1206        SETTING OUT OF WORK AND PROTECTION OF BEACONS

        The Contractor's attention is drawn to the requirements of Clause 17, Parts I and II of the Conditions of Contract regarding setting out.

        The original points, lines and levels of reference referred to in Clause 17 shall be those shown on the drawings.

        The Contractor shall survey all reference and level beacons and satisfy himself that they have not been disturbed and are true in regard to position and level.  If beacons have been destroyed, disturbed or damaged before the Site is handed over to the Contractor, the Engineer will arrange to have new beacons installed.  A beacon which has been disturbed shall not be used unless its true position and level has been re-established and the new values have been verified by the Engineer.

        Where a beacon is likely to be disturbed during construction operations, the Contractor shall establish suitable reference beacons at locations where they will not be disturbed during construction.  Beacons shall be established on a steel pin set in concrete or no other less permanent manner approved by the Engineer.  No beacon shall be covered over, disturbed or destroyed before accurate reference beacons have been established and details of the position and levels of such beacons have been submitted to the Engineer and approved by him.  The Contractor's reference beacons shall be of at least the same quality and durability as the existing beacons.

        The Contractor shall submit to the Engineer the method of setting out he proposes to employ.  Methods employed shall be such as to facilitate checking of line and level by the Engineer's inspectors without the use of survey instruments.  The Engineer may at any time request the Contractor to submit proof that his setting out has been satisfactorily checked.

        If any trigonometrical beacons, bench marks or other land survey marks are disturbed or destroyed by the Contractor they shall be replaced, within three months, by a registered land surveyor at the Contractor's expense.  In cases where displacement of or damage to such beacons is unavoidable the Contractor shall notify the Engineer in good time so that he may arrange to have such beacons suitably referenced and later on reinstated.  The cost of such work, if paid for by the Contractor, shall be reimbursable as defined in Clause 51 of the General Conditions of Contract.

        Accurate control of line and level shall be provided by the Contractor at all stages of construction.  In respect of the road itself control shall be at 20 m intervals, or such closer intervals as may be directed on horizontal and vertical curves.  Wherever necessary, but particularly on completion of the sub-grade and the base, the Contractor shall re-establish stake line pegs at sufficiently close intervals to determine accurately the edges of the base, surfacing and other road elements permanently exposed to the eye.

        Setting out will not be measured and paid for directly and compensation for the work involved in setting out will be deemed to be covered by the prices tendered and paid for the various items of work included under this Contract.

1207        NOTICES, SIGNS AND ADVERTISEMENTS

        The Contractor shall not erect any signs, notices or advertisements, on or along the Works or the Site of the Works without the written approval of the Engineer.

       

        The Contractor shall provide and erect, as part of his obligations under Section 1300 and on approved sites, signboards of sound weatherproof construction, painted by an approved firm of signwriters.  The format will be given by the Engineer. Four signboards will be required, two at Korovou and one each at the extremities of the Works.

        These signs are to be erected not later than one month after the Contractor has been given access to the Site.

        The signboards shall be painted with the legend in English.

        No signboards other than those specified above will be permitted on or adjacent to the Works, except that the Contractor may permit each of his sub contractors to display one, and only one, signboard of less than 2 sq. m at the works office.

        The Engineer shall have the right to have any sign, notice or advertisement moved to a better position or to have it removed from the Site of the Works if it should in any way prove unsatisfactory, inconvenient or dangerous to the general public.

        All advertisements, notices and temporary signs shall be removed by the Contractor by the end of the Maintenance Period.

1208        MEASUREMENT

        (a)        Units of Measurement

                All work shall be measured in accordance with the S.I. System of metric units.

        (b)        Bill of Quantities

                The quantities set out in the Bill of Quantities are estimated quantities and are used for the comparison of Tenders and awarding the Contract.  It must be clearly understood that only the actual quantities of work done or materials supplied will be measured for payment, and that the billed quantities may be increased or decreased as provided for by the General Conditions of Contract.

        (c)        Measurement of completed work

                (i)        All distances along the centre line of the roads or sewer line as shown on the Drawings are horizontal distances at sea level and these distances will be used in calculating the quantities of fill, sub-bases, bases, shoulders, surfacing and paving for payment purposes.  All cross sections shall be taken in a vertical plane.

                (ii)        All materials which are specified to be measured in the vehicle shall be hauled in vehicles of such type and size that the actual contents may be readily and accurately determined.  Unless all vehicles are of uniform capacity, each vehicle shall bear a plainly legible identification mark indicating its specific approved capacity.

               

                (iii)        Structures shall be measured to the neat lines shown on the drawings including any changes ordered in writing by the Engineer and shall include any reinforcing steel and minor ducts up to 150 mm in diameter.
1209        PAYMENT

        (a)        Contract Rates

                In computing the final contract amount, payments shall be based on actual quantities only of authorised work done in accordance with the Specifications and Drawings.  The tendered rates shall apply, subject to the provisions of the General Conditions of Contract, irrespective of whether the actual quantities are more or less than the billed quantities.

        (b)        Prices to be inclusive

                The Contractor shall accept the payment provided in the Contract and represented by the prices tendered by him in the Bill of Quantities, as payment in full for executing and completing the work as specified, for procuring and furnishing all materials, labour, supervision, plant, tools and equipment, for wastage, transport, loading and offloading, handling, maintenance, temporary work, testing, quality control including process control, overheads, profit, risk and other obligations and for all other incidentals necessary for the completion of the work and maintenance during the Period of Maintenance.

                This Clause shall be applicable in full to all pay items except as these requirements may be specifically amended in each case.

                In particular the Contractor shall be deemed to have included time related and fixed costs as specified in Section 1300 under the appropriate items in the General and Preliminary section of the Bill of Quantities and not in rates for work items.

        (c)        Meanings of certain phrases in payment clauses

                (i)        "Procuring and furnishing....(pay item mentioned) Material"
                        Where any of the words "supply", "procure" or "furnish" (material) are used in the description of a pay item it shall mean the supply and delivery to the point of use of all materials of any kind required for the work covered by the particular pay items, including all tax, purchase costs, claims, damages, royalties and transport costs involved.  In the case of borrow materials, stone and sand, it shall also include all negotiations with owners concerned, royalties, excavating, producing, preparing, processing, testing, hauling and delivering the material to the point of use; the construction, repair, maintenance and making good after completion of all access roads, and all work required in opening, using and finishing off borrow pits which is not covered by other pay items in the Bill of Quantities.

                (ii)        "Placing material"

                        The phrase "placing material" shall mean the offloading, spreading, blending, processing, watering, mixing, shaping and compacting (where specified) the material in the road prism, subbase, base, shoulders, banks and bypasses as well as procuring, furnishing, applying and admixing of water; breaking down oversize material, removing oversize material which cannot be broken down, correcting irregular or uneven surfaces or deficient thickness, finishing off to within the specified tolerances, refilling test holes and maintaining the completed work.  In the case of asphalt courses and bituminous treatments it shall also mean the heating and spraying of binder, spreading of aggregate or asphalt mixtures, rolling, compacting, finishing off to within the specified tolerances and maintaining the completed work.

                        The phrase "procuring, furnishing and placing" shall mean "procuring and furnishing" in addition to "placing" all as defined hereinbefore.

        (d)        Pay items

                The descriptions under the pay items in the various sections of the Specifications, indicating the work to be allowed for in the tendered prices for such pay items, are for the guidance of the Contractor and do not necessarily repeat all the details of work and materials required by and described in the Specifications.

                These descriptions shall be read in conjunction with the relevant Specifications and Drawings and the Contractor shall, when tendering, allow for his prices to be inclusive as specified in Subclause (b) above.

        (e)        Materials on Site

                No payment will be made in any Certificate for any materials on site until such time as they have been incorporated in the permanent works and approved.

        (f)        Provisional Sums

                The Bill of Quantities may contain certain Provisional Sums so designated and entered as a preliminary allowance to cover the cost of work, materials, goods or services to be provided by the Contractor and which have not been fully specified or measured or to cover the cost of unforeseen items of work or contingent expenditure.  Work done under a Provisional Sum shall only be executed upon a written order by the Engineer which order shall also specify the method of payment.  

                Payment as specified in the order given by the Engineer shall be either at the contract rates tendered or where the Contractor was not required to enter a rate in his tender then payment shall be in accordance with the provisions of Clause 58  of the General Conditions of Contract.  


1210        SUBSTANTIAL COMPLETION OF THE WORKS

        The Contractor shall note that the Engineer reserves the right not to certify the Works to be "substantially completed" as required by the General Conditions of the Contract, unless the following portions of the Works are completed according to the Specifications:

        (a)        the gravel wearing course, final bituminous surfacing and kerbing;

        (b)        all drains and drainage structures, for the construction of which timeous instructions were given by the Engineer;

        (c)        finishing of medians and slopes of cuts and fills to the road;

(d)        bridgeworks;


Opening of sections of the road or individual bridges to public traffic shall not entitle the Contractor to receive a Handing Over Certificate unless the section is separately  identified in the contract or qualifies otherwise in terms of Cl 48 of the General Conditions of Contract


1211        HAUL OVER COMPLETED ROAD

        The operation of hauling equipment over portions of the road completed up to the top of any stabilised layer, subbase, base, surfacing shall be limited to equipment with an axle load not exceeding that allowed by the Engineer.

        Notwithstanding any approval given by the Engineer to open any section of road to public traffic or the Contractor's own traffic, the Contractor shall be fully responsible for the rectification of damage to the sub-grade or underlying pavement that may be caused by such traffic.

1212        NOT USED



1213        NOT USED


       

1214        EXTENSION OF TIME ARISING FROM ABNORMAL RAINFALL

        (a)        The Contractor shall be granted extensions of the Contract Period in respect of rainfall deviating from average conditions defined hereunder. The Contractor is deemed to have examined all available information regarding the climate in the area of the site. The figures employed in the formula for calculating adjustments to the contract period given hereunder are average figures from a single rain gauge, the derivation of which are given in the information provided to tenderers.

                The adjustment to the Contract Period shall be calculated separately for each calendar month or part thereof in the manner set out hereunder and shall be calculated for the whole period for completion of the Contract including any extension thereof granted pursuant to Clause 44 of the General Conditions of Contract and any extension calculated in accordance with this clause.

        (b)        (i)        Adjustment of the Contract Period shall be calculated as follows :

                        V        =        (Nw - Nn) + (Rw - Rn)
                                                           30

                        The symbols have the following meanings

                        V        =        Adjustment of the Contract Period in calendar days in respect of the calendar month under consideration subject to limitations defined hereunder.

                        Nw        =        Actual number of days during the calendar month upon which a rainfall of 10mm or more has been recorded.

                        Nn        =        Average number of days upon which more than 10mm was recorded, as derived from rainfall records described in Subclause 1214 (c).

                        Rw        =        Actual rainfall in mm in respect of the calendar month under consideration.

                        Rn        =        Average rainfall in mm in respect of the calendar month under consideration as derived from records described in Subclause 1214 (c).

        (ii)        If the Engineer considers the Contractor to be entitled to an extension of the contract period pursuant to Clause 44 for reasons other than exceptional adverse climatic conditions, due account shall be taken in computing the extension of time due, of the seasonal climatic conditions under which the Works will be performed.  As such, the extension of time computed pursuant to this Clause shall be considered a full and fair allowance for variations from the average weather conditions during the course of the Works.

        (iii)        The formula does not take account of flood damage (arising other than from failure on the part of the Contractor to provide adequate temporary protection of partly completed Works) which causes further of consequential delays.  Such further delays shall be considered separately in accordance with Clause 44 of the General Conditions of Contract.

        (iv)        Average values for Nn and Rn have been extracted from historical records relating to Station V7885C P074 at Korovou

        MONTH
        STATION V7885C P074
                        Rn        Nn
        JANUARY                292        8.3
        FEBRUARY                276        8.3
        MARCH                347        10.4
        APRIL                324        8.4
        MAY                 213        6.1
        JUNE                 123        3.5
        JULY                 111        3.0
        AUGUST                 124        3.5
        SEPTEMBER                 129        4.3
        OCTOBER                157        5.2
        NOVEMBER                 226        7.2
        DECEMBER                240        7.6

        (v)        The value of V shall be limited to maximum and minimum values in respect of the calendar month under consideration as follows:

                (a)        If V is negative and its absolute value exceeds Nn then V shall be taken as equal to minus Nn.

                (b)        If V is greater than the figure tabulated hereunder in respect of the month and gauging station under consideration then V shall be taken as equal to the tabulated figure.

        JAN        FEB        MAR        APR        MAY        JUN        JUL        AUG        SEP        OCT        NOV          DEC

        14        11        12        14        16        21        21        21        20        19        17         15

        (vi)        Negative values of V shall be disregarded when applying the provisions of this clause to any extension of the contract period that has arisen as a result of calculation pursuant to this clause.

        The total adjustment of the Contract Period shall be the algebraic sum of the monthly totals for the time for completion or extended time for completion.

        Extensions of time for part of a month shall be calculated using pro rata values of Nn, Rn and figures tabulated in Subclause 1214 b (iv) above.

        If the total is negative, the time for completion shall not be reduced.

(c)        (c)        For the purpose of this clause, actual rainfall measurements shall be those made at Station V7885C P074 at Korovou.

(d)        No additional cost whatsoever shall be certified in respect of any extension to the contract period arising pursuant to this clause whether included in the Bill of Quantities as a time related item or not, except  where the payment is in respect of a service provided to the Engineer's supervisory staff.

1215        THIS CLAUSE HAS NOT BEEN USED.

1216        INFORMATION FURNISHED BY THE EMPLOYER

        Certain information contained in these Contract Documents or provided separately is being offered in good faith but in the circumstances pertaining to the type of information supplied, no guarantee can be given that all the information is necessarily correct or representative of the in situ conditions.

        More specifically this applied to all deflection surveys, soil tests, soil mapping, drilling results, geophysical surveys, geological reports, borrow pit information, material surveys and reports and similar information, the accuracy of which is necessarily subject to the limitations of testing, sampling, the natural variation of material and formations being investigated and the measure of certainty with which conclusions can be drawn from any investigations carried out.

        It also applies to any Material Utilisation Diagram supplied, as the diagram may be subject to major alterations during the progress of the work, depending on site conditions.

        The Employer accepts no liability for the correctness or otherwise of the information supplied or for any resulting damages whether direct or consequential should it prove during the course of the Contract that the information supplied is either not correct or not representative.  Any reliance placed by the Contractor on this information shall be at his own risk.

1217        THIS CLAUSE HAS NOT BEEN USED

1218        PROTECTION OF THE WORKS AND REQUIREMENTS TO BE MET BEFORE CONSTRUCTION OF NEW WORK ON TOP OF COMPLETED WORK IS COMMENCED

        (a)        The Contractor is to provide temporary drainage works such as drains, open channels, banks, etc. and the furnish and operate temporary pumps and such other equipment as may be necessary to adequately protect, drain and dewater the works and temporary works.  This will be in addition to any permanent drainage works specifically paid for separately.

        (b)        Care shall be exercised not to allow material in borrow pits to become excessively wet, to keep all completed layers properly drained, not to cause dumps of material on completed layer work to inhibit surface drainage or to form wet spots under and around dumps, and to protect all parts of the work against erosion by floods and rain.

                Material shall not be spread on a layer that is so wet such as to damage underlying layers or prevent adequate compaction of overlying layers. Such wet layers shall be dried and recompacted or removed.

        (c)        Fill and cut slopes shall be promptly repaired whenever damaged by surface water.  Where erosion occurs on high fill, the slopes shall be repaired by cutting back to form benches and compacting the backfill mechanically to the specified controlled densities, using suitable small equipment.

        (d)        Excavations for pipe drains, culverts, sewer drains, water mains, manholes, service ducts and similar structures shall be adequately protected against the possible ingress of water during rainstorms.

        (e)        All completed layer work shall be protected and maintained until the following layer is applied.  Maintenance shall include immediate repairs to any damage or defects which may occur and shall be repeated as often as is necessary to keep the layer continuously intact and in a good condition.

        (f)        Before any completed layer is primed or a succeeding layer constructed thereon, any damage to the existing layer shall be repaired so that after repair or reconstruction if necessary, it will conform in all respects to the requirements specified for that layer.  All repair work other than minor surface damage repairs shall be submitted to the Engineer before covering up.

                The previously constructed layer shall also be thoroughly cleaned of all foreign material before construction of a succeeding layer or application of a prime coat, surfacing or surface treatment. The existing layer shall be thoroughly broomed and all dung, clay, mud and other deleterious material completely removed.  Where necessary, the surface shall be sprayed with water before, during and after brooming to remove all foreign material.

                Work performed as part of the above obligations shall not be measured and paid for separately and the cost thereof is to be included in the prices tendered for the various items of work requiring protection and for the Contractor's establishment on Site as specified in Section 1300.




1219        REMEDIAL WORK

        When any part of the Works or any equipment or material is found upon examination by the Engineer not to conform to the requirements or is at any stage before final acceptance damaged so that it no longer conforms to the requirements of the Specifications, the Engineer may order its complete removal and replacement, at the Contractor's expense, with satisfactory work, equipment or material or he may permit the Contractor to apply remedial measures in order to make good any such defects or damage.  The actual remedial measures taken shall at all times be entirely at the Contractor's own initiative, risk and cost, but subject to the Engineer's approval regarding the details thereof.
   
        In particular, remedial measures shall ensure full compliance with the Specifications of the final product, shall not endanger or damage any other part of the Works and shall be carefully controlled.

        For the guidance of the Contractor an indication is given below of what would normally be required in the more common cases of defects or damage, but the Engineer will in no way be bound to approve of or adhere to the measures given below as the actual remedial measures will be dictated by the circumstances of each particular case.

        (a)        Earthworks

                (i)        Where a cut slope has been over-excavated or undercut, backfilling will not normally be allowed and the entire slope may have to be retrimmed to obtain a uniform slope.

                (ii)        Where the floor of a cutting has been taken too deep, it will normally require backfilling and recompaction with selected gravel in the case of soil or gravel excavation and with crushed stone material or suitably sized rock in the case of hard excavations.  All necessary measures shall be taken to drain away ground water that may accumulate in backfilled sections.

                (iii)        Excess width of fills will have to be trimmed down.

                (iv)        Where erosion has damaged the surface of cuts or fills the damage shall be made good by backfilling with suitable material and retrimming.  In more serious cases benching may have to be cut back and backfilled by compaction with suitable small equipment and then retrimmed.

                (v)        Where excavated material has been allowed to spill over the edge of existing slopes, this surplus material shall be removed and the vegetation of the slope reinstated.

        (b)        Stabilising

                Any sections failing to meet the requirements specified or damaged to the extent that they require breaking up and recompaction will have to be restabilised with the type and quantity of stabilising agent ordered by the Engineer.  The Engineer may also order that the layer be removed entirely and replaced with fresh material to be stabilised.
       
       



        (c)        Local defects in pavement layers

                Where remedial measures are taken to make good local defects, the length and width of the area to be repaired by machines shall be such as will be necessary to accommodate the full width of the machines used and a reasonable length to ensure effective operation.

                The depth to which material will have to be removed will depend on the type of material.  Gravel will require breaking up to a depth of at least 75 mm and crushed stone will usually require breaking up over its full depth.  Asphalt material will normally require removal for its depth.

        (d)        Concrete

                Concrete work will normally require the cutting back and complete removal of any weak or honeycombed sections and making good using special epoxy adhesives to bind fresh concrete to old concrete.  Cracks, when permitted to remain, shall be injected with suitable epoxy compounds and test cores drilled to test the efficiency of the injection process.

1220        WATER

        The Contractor shall make his own arrangements for procuring, transporting, storage, distribution and application of water needed for construction and other purposes, except where otherwise specified.  No direct payment will be made for providing water and the cost thereof shall be included in the prices tendered for the various items of work for which water is needed.

        Only clean water, free from undesirable concentrations of deleterious salts and other materials shall be used.  The Contractor shall ensure that sufficient supply of water is at all times available to ensure continuity of work.  All sources of water used must be approved by the Engineer.

1221        ELECTRICITY SUPPLY

        The Contractor shall provide and maintain at his own expense his own electrical supply.  This supply must be adequate to supply the areas set aside for the housing of his staff and for his own and the Engineer's Office, and for any housing of the Engineer's staff.

        The Contractor shall provide and maintain all necessary temporary power and lighting and all associated apparatus for the duration of the Contract at his own expense.

        Once equipment becomes redundant and having received the approval from the Engineer the Contractor shall disconnect and remove said equipment and make good any works disturbed at his own expense.

1222        PAYMENTS AND TOLERANCES

        The work specified in the various sections of these Specifications shall comply with the various dimensional and other tolerances specified in each case.  Where no tolerances are specified, the standard of workmanship shall be in accordance with normal good practice.

        No representation is made that the full specified tolerances will be available independently of each other and the Contractor is cautioned that the liberal or full use of any one or more tolerances may deprive him of the full or any use of tolerances relating to other aspects of the work.  The latter would apply particularly in respect of level tolerances on layer work and the related requirements regarding layer thicknesses.

        In the description of certain pay items, where it is stated that quantities will be determined from the "authorised" dimensions, this shall be taken to mean the dimensions as specified or shown on the Drawings or, if changed, as finally instructed by the Engineer, without any allowance for tolerances specified.

        If the work is therefore constructed in compliance with the "authorised" dimensions plus or minus any tolerances allowed, quantities will be based on the "authorised" dimensions regardless of the actual dimensions to which the work is constructed.

        Where the work is not constructed in accordance with the "authorised" dimensions, plus or minus any tolerances allowed, the engineer may nevertheless in his sole discretion accept the work for payment.  In such cases no payment will be made in respect of quantities of work or material in excess of those calculated from the "authorised" dimensions and where the actual dimensions are less than the "authorised" dimensions, minus any tolerance allowed, quantities for payment shall be based on the actual dimensions as constructed.

1223        DRAWINGS

        The Contractor shall prepare neat, stencilled, true to scale reproducible drawings on plastic film of the whole works "as constructed".  The drawings shall be produced to a standard similar to that of the Contract Drawings.

        Record drawings shall include the positions and extent of all support construction left in any excavations and exact locations of all services encountered during construction.  The Contractor shall also prepare annotated longitudinal sections showing soils encountered during all excavation work.

        For all reinforced concrete structures record drawings shall be prepared showing all reinforcement "as fixed".

        Record drawings shall be prepared to the Engineer's approval as the work proceeds and shall be handed to the Engineer on completion.  The Record Drawings shall then become the property of the Employer.

        Should the Contractor require further drawings that may be necessary for the execution of the Works he shall prepare and submit such detailed drawings with adequate notes in writing for the Engineer's approval.

        The Engineer may within a reasonable period approve, amend or change these drawings or may require the Contractor to produce amended drawings.  All drawings shall be subject to approval by the  Engineer but any approval of drawings shall not relieve the Contractor of any of his obligations under the Contract.

        Accepted drawings shall form an integral part of the Contract Documents and any drawings not accepted and signed shall not be permitted on the Site of Works for construction purposes and/or used for the manufacture of any item.  Notwithstanding the approval and/or acceptance and signing of the drawings the Contractor shall take full responsibility for all details, discrepancies, omissions, errors, etc. in respect of the said drawings as well as the consequences thereof.       

        The Contractor shall submit only fully completed drawings in accordance with this specification and shall not be entitled to claim for delays resulting from the submission of incomplete drawings.  The Engineer shall require a period of four to eight weeks depending on circumstances, for reviewing the complete drawings.

        No direct payment for design preparation and submission of drawings shall be made and all costs shall be included in the prices tendered for the relevant pay items as provided for in the Bill of Quantities.  The cost of reviewing the design/drawings shall be at the Contractor's expense if the necessity for such review arises from alternative designs proposed by the Contractor, designs of temporary works or necessary for rectification or remedial works.


1224        NOT USED


1225        PHOTOGRAPHIC RECORDS

        The Engineer shall make photographs and other records to be agreed with the Contractor of the condition of the surfaces of the site immediately before entering upon them for the purpose of constructing the Works.

        Each month, the Engineer shall make a set of up to 36 colour photographs illustrating progress of the Works, or any other photograph that he may deem necessary for record purposes.
        The Contractor shall reimburse to the Engineer the cost of films, development and printing of two sets of photographs per film and the cost of good quality photograph albums sufficient to accommodate 36 photographs per month for the duration of the construction period.

        The Contractor may at his option arrange for further copies of any of the Engineer's record photographs at his own cost and the Engineer shall make the negatives available to him for that purpose, or arrange copies on the Contractor's behalf at his sole discretion.

        The copyright of all photographs shall be vested in the Employer and the Contractor shall not use any photograph for any purpose whatsoever without the Engineer's approval.

1226        THIS CLAUSE HAS NOT BEEN USED.

1227        ACCESS TO SITE

        The Contractor shall make his own arrangements for access to the various parts of the Site where works are to be constructed but all such accesses shall be subject to the approval of the Engineer.

        Where the access to the Site proposed to be used by the Contractor lies across the land of any third party the Contractor shall produce to the Engineer the written consent of the owner and the occupier of the land over which the access lies before making use of the same.

        The Contractor shall also make a record to be agreed by the Engineer of the conditions of the surfaces of any land (and of any crops on such land) over which access lies before he uses it for access purposes and he shall keep all such surfaces in a reasonable state of repair during the executing of the Works.  On the termination of the Contractor's use of such access he shall restore any lands, roads or other property to a condition at least equal to that existing before his first entry upon them.

1228        CO-OPERATION AT SITE

        All work shall be carried out in such a way as to allow access and afford all reasonable facilities for any other contractor and his workmen and for the workmen of the Employer and any other person who may be employed in the execution and/or operation at or near the site of any work in connection with the Contract or otherwise.

        The Contractor shall use his best endeavours to co-operate with such persons without interfering with them and shall observe all the instructions and orders of the Engineer in that connection.

        In the preparation of his programme of work the Contractor shall at all times take full account of and co-ordinate with the programming of work of other contractors.

1229        ROADS AND SITE TO BE KEPT CLEAN

        The Contractor shall take great care and all reasonable precautions to ensure that roads and thoroughfares used by him either for the construction of the Works or for the transport of plant, labour and materials are not made dirty as a result of such construction or transport and in the event of their becoming thus dirtied in the opinion of the Engineer the Contractor shall take all necessary and immediate steps to clean them.


1230        SECURITY OF THE WORKS

        Watching of the Works shall be provided by the Contractor at his own expense.  If the Engineer considers it necessary he will order in writing that additional watchmen be provided all at the Contractor's expense.

1231        SUPPRESSION OF NOISE

        The Contractor shall make every reasonable endeavour both by means of temporary works and by the use of appropriate plant or silencing devices to ensure that the level of noise resulting from the execution of the Works does not constitute a nuisance.

1232        SAFETY

        The Engineer shall be notified by the Contractor immediately any accident occurs whether on Site or off Site in which the Contractor is directly involved which results in any injury to any person whether directly concerned with the Site or whether a third party.  Such initial notification may be verbal and shall be followed by a written comprehensive report within 24 hours of the accident.

        Transportation of any material by the Contractor shall be in suitable vehicles which when loaded do not cause spillage and all loads shall be suitably secured.  Any vehicle which does not comply with this requirement or any of the local traffic regulations and laws shall be removed from the Site.

1233        METHOD OF WORKING

        The Contractor shall adopt a method of working such as to permit the satisfactory and timely completion of the Works and to limit disturbance and damage to a minimum.

        The Contractor shall only open up sections of the Works for which his resources are sufficient to maintain continuous and methodical progress.  If in the opinion of the Engineer, the Contractor has not complied with the foregoing, he shall be entitled to suspend sections of the works pursuant to Clause 40(d) of the General Conditions of Contract until other sections have been completed to a stage where risk of damage through exposure to traffic and the elements and inconvenience to public traffic has been minimised.

        Constructional Plant used in the execution of the Works shall be of a design and used in a manner approved by the Engineer.

        The Engineer may at any time withdraw his approval for any method of working proposed by the Contractor and the Contractor shall immediately adopt another method of Working.  If such change shall be required to achieve satisfactory progress or workmanship, the Contractor shall have no claim against the Employer for costs incurred by him in changing the method of working or in the provision and use of other plant.

1234        TEMPORARY WORKS

        The Contractor shall provide, maintain and remove on completion of the Works all temporary works necessary for the construction of this permanent works.  All temporary works shall be properly designed and constructed to carry such loads as may be imposed upon them and shall be safe and suitable in every respect for providing access or carrying plant or for the construction of the Works or other purposes.
        The Contractor shall, at least 28 days before the commencement of any part of the Works, submit, in duplicate, drawings and calculations relating to the strength, stability and anticipated defections in respect of all temporary works and showing the methods he proposes to adopt for the construction of the various parts thereof.

        Any modifications that the Engineer may require, either before, during or after construction of the temporary works, shall be made by the Contractor without charge.  No approval or alteration made on the instructions of the Engineer of any submitted design or any of the temporary works shall relieve the Contractor from any liability or obligation under the Conditions of Contract in respect of such temporary works.  The Contractor shall be responsible for all negotiations with public or private bodies concerned relative to temporary works.  All proposals for temporary works shall be sent to the Engineer for comment before submission to such bodies.
回复 支持 反对

使用道具 举报

您需要登录后才可以回帖 登录 | 注册

本版积分规则

特别声明:本站资料全部来自互联网和网站会员上传,若侵犯作者权益请与本站联系,我们将在24小时内删除!
管理员:〖快乐小屋〗 QQ:273469910 邮箱:273469910@qq.com

QQ|Archiver|手机版|【天端--工程在线】    

GMT+8, 2024-11-10 20:50

Powered by Discuz! X3.2

© 2001-2013 Comsenz Inc.

快速回复 返回顶部 返回列表